Sunday, 11 December 2016

Surveying Equipments and Level Set up

SURVEYING EQUIPMENT AND LEVEL SET-UP

The opposite figure shows a LEICA Level packages.

Make sure the surveying equipment you will borrow is reliable and in good working order.

To ensure this a two peck test must be carried out each 
time you borrow a level.

Surveying instruments that you need to complete your projects, 
can be borrowed from the following persons:


Equipment

For carrying out your project work you need to borrow the following equipment:

LevelTripodStaff (5 metre)
Staff bubbleMeasuring tape (50 metre)Wooden pegs (if needed)

Additional equipment is needed for some other projects and the lecturer will inform you what you need to do this exercises.

The following information is extracted from 'LEICA NA720 User Manual'.

Level types
There are different types (Leica, Sokkia, Wild) of levels you can borrow. The level opposite is a Leica NA720. Most level instruments have an automatic horizontal adjustment of the line of sight. Levels are supplied in a case in which the instrument can be shock proof stored. All survey levels operate in a similar way. The function and operation of levels is explained using the Leica 720 which is the most available instrument in the storerooms.
Endless drive (both sides)Bubble level (to check horizontal plane)Mirror to view bubble levelBase plate (sits on tripod)Footscrew (to adjust the horizontal plane)Eyepiece (focus adjustmentKnurled ring (for horizontal circle reading)ObjectiveCourse aiming deviseFocusing knob (turn until staff reading is clearly visible)Window for digital angle reading (see 7)

Setting up the tripod




Loosen screws of tripod legs, pull out to required length and tighten screws.In order to guarantee a firm foothold sufficiently press the tripod legs into the ground. When pressing the legs into the ground note that the force must be applied along the legs.Check all screws and bolts for correct fit.When setting up the tripod pay attention to a horizontal position of the tripod plate. Minor inclinations of the tripod can be corrected with the footscrews of the tribrach.Place level onto tripod head. Tighten central fixing screw of tripod.Turn footscrews A and B simultaneously in opposite directions until bubble is in the centre (on the imaginary "T").Turn the instrument 90° and then turn the foot screw C until bubble is centred.If you want to centre an instrument over a ground point:

  1. Attach plumb bob and arrange the tripod in such way that the plummet is over the point.
  2. For fine adjustment loosen central fixing screw slightly and shift instrument parallel on tripod until the plummet is exactly over the point.
  3. Tighten central fixing screw.

Focusing telescope

Aim telescope against a bright background (e.g. white paper).

Turn eyepiece until reticule is sharp-focused and deep black. Now the eyepiece is adapted to your eye.

Aim telescope on staff using the coarse aiming device.

Turn focusing knob until image of staff is sharply focused.

Levelling staffs (rods) and accessories

There are many types of staffs, with names that identify the form of the graduations and other characteristics. Staffs can be one piece, but most of them are sectional and adjust the length by telescoping..

The metric staff has major numbered graduations in meters and tenths of meters (there is a tiny decimal point between the numbers). Our staves have an ''E'' shape mark (or its mirror image) with horizontal spaces between them of 10 mm.

When viewed through an instrument's telescope, the observer can easily visually interpolate a 10 mm mark to a quarter of its height, giving a reading accuracy of 2.5 mm. On one side of the rod, the colours of the markings alternate between red and black with each meter of length.

The Black arrows indicates where to push to extend the staff to its full length.

                                                                

Staff readings

The figure below shows three different staff readings:

It is easy to read (b) and (c) because the cross-hair is exactly on a mark division. The reading for (a) is between 1.630 and 1.640. To assess the mm reading you have to estimate where the position of the cross-hair is. For (a) the reading is 1.636. The millimeter reading is to be estimated and can very between ± 1 mm.

reading (a) is 1.636 (b) is exactly 1.500     and (c) is 1.580


Spirit & line levels

There are a wide range of spirit levels to meet the varying requirements of specific jobs. The majority of those used on construction work are made of powder coated aluminum or die cast construction. The length varies from 800 mm to 2000 mm. Spirit levels are very handy for short distance levelling (depending on the spirit level up to 2 metres and with straight edge up to approximate 5 metres). The straight edge is used if the the points to be levelled exceed the length of the spirit level.

The line level has been designed and made with two small hooks to hold it on a line as shown in the figure above. A line level is a level designed to hang on a string line. The level must hung in the center of the string and each ''leg'' of the string line extends the levels plane.
The line level is a simple surveying instrument which can be used to lay out contours and gradients, and also to assist measuring horizontal distances at slope.

Plumb bobs

 A plumb-bob or a plummet is a weight with a pointed tip on the bottom that is suspended from a string and used as a vertical reference line. This instrument has been used since the time of the ancient Egyptians by bricklayers, masons, and carpenters to ensure that their constructions are "plumb", or perfectly upright. It may also be used in surveying to sight a point on the ground that is not readily visible. Small plumb bobs are often included in the kits of various instruments such as levels and theodolites. They are used to set the instrument exactly over a fixed datum marker, prior to taking fresh readings. In conjunction with the line-level the can also be used to assist the horizontal measurement on slopes.

Water level

An old device but a simple instrument for measuring the level differences of two points. This level, is illustrated in the opposite figure. The two levelling staffs are of the same length with a graduated tape attached to each stave. The tube is filled with water. The ends of the tube are fitted with rubber stoppers to prevent loss of water. The total length of tube defines the range of the instrument.


Straight edge

A 'straight edge' in conjunction with a spirit level and tape measure can be used to establish a gradient. The straight edge is usually 3 to 5 metres long and set horizontally with the aid of a spirit level. This method should be used for the measurement of gradients which continue only for short distances, e.g. to calculate the horizontal distance shown in plan-views. The figure below shows how a gradient for the ground profile is found.



Measurements along a slope

Distinguish between a horizontal distance and a slope distance. All distances should be measured 'horizontally'. Do not measure along slopes. Sag (tape are not supported for its length will sag under the influence of gravity) and to a lesser extent temperature may have an effect on the distance measurement also. To reduce the sag break tape measurement into shorter lengths.


The sum of horizontal lengths (L1 & L2) equals the horizontal distance of the slope from A to C. Remember the horizontal distance is always shorter than the measurement on the slope.

For an accurate measurement, the tape should be held horizontal and straight with a specified tension applied to it.

Slopes - Gradient calculations

A slope is the steepness, incline, gradient, or grade of a straight line, and it is defined as the ratio of the "rise" divided by the "run" between two points on a line. The gradient of a straight line shows how steep a straight line is. The slope of a line in the plane containing the y (rise) and x (run) axes may be represented as:

(a) gradient      (1:50;  1:2)
(b) percentage  ( 2%; 50%)(c) decimal fraction  (0.02;      0.5)
(d) angle                  (1.146°;  26.565°) 

Here are the calculation example of the figures shown in the "Straight edge" section

(a) Gradient     200 : 3000 = 1 : x     x = 15     Gradient = 1 :15

(b) Decimal fraction 200/3000 = 0.066666     Fraction = 0.0667

(c) Percentage multiply decimal fraction by 100
                     0.06666 × 100 = 0.06666            Percentage = 6.667%

(d) Angle in degree inverse tan-function rise over run (tan-1 function on calculator)
         tan a = 200/3000 = 0.06666                     a = 3.814°

Distance measurement methods

For measuring a distance we use steel or fibre glass tapes as shown in the opposite figure. They are available in 30 metre and 50 metre length.

A more sophisticated method is to use the Electronic Distance Measuring (EDM).
We will not use this method. EDM devices use electromagnetic waves, infrared waves, or lasers to measure distances precisely.

Approximate (fairly accurate) distance measurement method is 'pacing' or using the 'stadia lines' on the reticle of the level
Pacing
Don't try to pace out one metre with every step. Walk casually over 50 or better 100 metre counting the number of steps. Work out the length of a casual step and use this instead. The longer the walking distance the more accurate is the step measurement.
Example
If it takes you 65 steps to walk 50 metres; then your step is 50/65 = 0.77 metre. If you would waked 39 steps, then the distance is 39 x 0.77 = 30 m.
Stadia lines
The stadia lines on the reticle can be used for simple distance measurement. The distances intercepted on the vertically-held rod between two stadia hairs seen in the eyepiece gives the distance. Just multiply the difference on the rod between the top and bottom stadia lines by 100* as shown in the figure below.


In the example above the distance between the top and bottom stadia hair is 62 mm. Therefore, the distance to the staff is 62 × 100 = 6200 mm or 6,2 metres.
The 100 figure should be checked before beginning any survey by measuring the known distance with a tape.

Surveyors usually use total stations for land surveying. A total stations is a combination of an electronic theodolite (transit), and electronic distance measuring device (EDM).

Other accessories

Optical square





Range PoleOpticle Square and Range Poles are used in surveying course No W5939


Change Plate - a small flat metal plate with a raised point in the centre that is used to support the staff on the ground. The plate is firmly embedded into the ground to stop the staff from subsiding.
There are various types of staff bubbles available to assist in keeping the staff in an upright position.
You will need pegs or stakes and hammer for Project 4 (Grid points for RL's) All can be borrowed from the surveying department.

List of Newly Registered Surveyor For the year 2016


SURVEYORS COUNCIL OF NIGERIA [SURCON]
[ESTABLISHED BY CAP S18 LAWS OF THE FEDERATION
OF NIGERIA 2004]
2016 PROFESSIONAL EXAMINATIONS RESULTS
The Council at its 76th meeting held on Thursday, 8th
December 2016 approved the results of the 2016
Professional Examinations. The results are as follows:
A. REGISTRATION OF SURVEYORS
Council approved that the underlisted candidates, having
satisfied SURCON requirements in the 2016 Professional
Examinations, are qualified to be registered as Surveyors
in accordance with Section 9(3) of the Enabling Act. They
are however expected to meet the financial conditions
stipulated in the letters sent to them, conveying the
Council’s approval.
SERIAL NO. CANDIDATE’S NAME EXAMINATION NO.
1 NWUNE TAGBO M. S2008/133
2 OKORIE DANIEL ERASTUS OGBONNA S2010/003
3 JOE INI-ABASI BENSON S2010/112
4 BABAWANDE AKANNI AKINDELE S2010/117
5 OMOTUYOLE OLUWABIYI OLUWASEUN S2011/065
6 ONYIA JONATHAN CHUKWUDI S2012/104
7 KAREEM ONIMISI YAHAYA S2012/137
8 SAHEED WALIU ADEWUMI S2013/051
9 OLUWAJUYITE LAWRENCE OJO S2013/057
10 AKANBI ABDULQADIR BOLAJI S2013/079
11 URUA UDOH USUNG S2013/081
12 UCHENDU CHUKWUMA PETER S2013/083
13 AKINSANYA OLUSEGUN AKINWALE S2013/097
14 DURU TOCHUKWU ADINDU S2013/114
15 UGWUOTI AMOS ILOABUCHI S2013/130
16 MBACHUKWU IZUCHUKWU S2013/147
17 ESAN MATTHEW ADEBAYO S2013/151
18 AJIBODE ABAYOMI OLANIRAN S2013/154
19 SANUARA ISRAEL OLALEKAN S2013/158
20 EBITIGHA ADEYEMI OLUWASOMI S2013/163
21 OLANREWAJU SUNDAY OLABODE S2013/168
22 EDUN MICHAEL DOLAPO S2013/193
23 AGBO ENEMONA SUNDAY S2014/001
24 ADAMU APAGU AYUBA S2014/014
25 ADEDOKUN SULAIMAN ADELANI S2014/016
26 ADEGBOLA OLUWOLE ADETUNJI S2014/018
27 ADEJUMOBI KAMORUDEEN OKE S2014/021
28 ADELEKE JOEL OYETUNDE S2014/024
29 AGU FRANCIS NNAEMEKA S2014/043
30 AIYENUGBA ADESINA BIDEMI S2014/045
31 AKPA CHISOMAGA JAMES OWEN S2014/058
32 AKPAGU EMENIKE JOE S2014/059
33 AKPAN BENAIAH MICHAEL S2014/060
34 AKPATA SYLVESTER BALM MIFUEAH S2014/061
35 ALAO ADEMOLA ADEROJU S2014/064
36 AMBALI SULAIMAN OLUWAKAYODE S2014/068
37 ANWANA JOHN OKON S2014/071
38 AREMU OLUGBENGA IDOWU S2014/073
39 AYOOLA BAMIDELE ESTHER S2014/079
40 AYOOLA OLUWASIJI IFEOLUWA. S2014/081
41 EKPO ATIM JUSTIN (MRS.) S2014/105
42 OBATA UJUNWA STELLA (MRS) S2014/111
43 FOLARIN EKUNDAYO S2014/122
44 GBELEKALE ADEBUKOLA ADEFUNKE S2014/124
45 HENRY USO USO S2014/131
46 IKPI OMOVIGHO RAWLINGS S2014/141
47 IMUNAN DENEN S2014/143
48 ISHAYA JOHN MUSA S2014/146
49 JAMAN TUNDE STEPHEN S2014/150
50 MAEBU VINCENT LESOR S2014/161
51 MAJEKODUNMI TUNDE S2014/162
52 NWANERI CHUKWUEMEKA CHUKWUEBUKA S2014/172
53 ODUWOLE AKINPELUMI RICHARD S2014/187
54 OGUDULOLA TITILAYO OMOLARA S2014/193
55 OHIKHUEME ANTHONY IKHIDE S2014/198
56 OJO ALEXANDER ADENIYI S2014/202
57 OKEKE CHUKWUEBUKA ANTHONY S2014/205
58 OKUNOLA ADEBOLA OLUWAKEMI S2014/210
59 OLADEJI MAYOWA OLALEKAN S2014/212
60 OPOOLA OLUWASEUN GBENGA S2014/227
61 SHITTU MOHAMMED SOFIYULLAH S2014/244
62 HENSHAW EDEM EFFANGA S2014/266
63 ANIERO UDUEZUE HILARY CHUKWUDUBEM S2014/273
64 RAPHEAL BLESSING S2014/280
65 EZE MAKUACHUKWU ALEXANDER S2015/004
66 OLOJEDE OLUWADAMILARE AYOBAMI S2015/012
67 ONYEKA INNOCENT IKECHUKWU S2015/015
68 AKPAN IFREKE MAY S2015/016
69 ONYIRIUKA OKECHUKWU CHIMAOBI S2015/017
70 SALEH MARKUS S2015/019
71 IBRAHIM NUHU S2015/021
72 OJO AYODEJI TOLULOPE S2015/023
73 MAGAJI ANTHONY DANJUMA S2015/024
74 ATTA-GIWA KAKA ZENABU S2015/026
75 UMAR HUSSAINI S2015/028
76 ONI OLUWASEUN OLUWABUNMI S2015/030
77 USMAN SADIQ ABDULRAHMAN S2015/031
78 IREKPITA BEAUTY PHILOMENA S2015/035
79 OKON DANIEL JONATHAN S2015/044
80 WAHAB MOJEED ADEKUNLE S2015/049
81 EMIEMU CLIFFORD S2015/050
82 OGUNYEMI STEPHEN FEMI S2015/051
83 ONI SAMSON KAYODE S2015/056
84 TAIWO ISRAEL OLUWASEUN S2015/057
85 OKEKE OKECHUKWU COSMAS S2015/058
86 OBIDIRE UZOCHUKWU KENECHUKWU S2015/060
87 USMAN AHMED S2015/064
88 KYRIAN SUSAN EMMANUEL S2015/066
89 OLORUNSHOLA OLUWAFEMI OREOLUWA S2015/069
90 AKPAN JULIUS UWEM S2015/072
91 ABISINE CLINTON AGOSIMIME S2015/075
92 KUMUYI SUNDAY JACOB S2015/078
93 ONWUASOANYA CHUKWUEMEKA OBIORA S2015/080
94 IBITOYE YOMI SAMSON S2015/081
95 GBADURA RUFUS S2015/083
96 ADRA AHMAD S2015/085
97 IGE MOFOLUTO ADEGBOLA S2015/086
98 INYANG OKON ASUQUO S2015/090
99 MAPADERUN OLUWASEYI TOLA S2015/091
100 MOHAMMED ABDULKARIM S2015/092
101 IDIGO ANTHONY CHINEDU S2015/098
102 TAIWO KAFAYAT OMOWUMI (MRS) S2015/101
103 YUSUF FATIMOH BOLANLE (MRS) S2015/102
104 EYITAYO-OLOTU BOSEDE MOLAYO S2015/105
105 BURAIMOH KOREDE SAMUEL S2015/108
106 LASISI AJANI JUBRIL S2015/109
107 IMHOMOH OSHIOTSE ALEXANDER S2015/110
108 IKUSIKA RUFUS SUNDAY S2015/111
109 OLASUPO RUFUS OLAOLA S2015/112
110 RAJI ADEGBOYEGA ISIAKA S2015/114
111 ADEDIJI MOSHOOD FOLORUNSO S2015/115
112 FESTUS AYEBAKURO CHARLES S2015/118
113 ADEYEMO DAVIES OLUSEGUN S2015/120
114 NNADI CHIDIMMA BRIDGET S2015/123
115 OBIDIMMA KENECHUKWU NNAMDI S2015/124
116 KANU PETER NNAMDI S2015/126
117 JACK PHILIP ASUQUO S2015/127
118 UDOUDO DANIEL OKON S2015/129
119 OKOROAFOR VICTOR CHUMA S2015/130
120 BINUYO VICTOR OLUBUSOLA S2015/138
121 OSAGBEMI BAMIDELE DAVID S2015/140
122 GARBA MUHAMMED S2015/141
123 OBAJE CALEB CHAPI S2015/150
124 NNAM UCHECHUKWU GODWIN S2015/151
125 OLATUNDE FAITH OZOFU (MRS) S2015/158
126 EMENGINI EBELE JOSEPHINE S2015/168
127 EZEOMEDO INNOCENT CHUKWUKALO S2015/172
128 OLUSANYA ALBERT OLAREWAJU S2015/176
129 ONOMAKE EMUOBOSA STEPHEN S2015/178
130 UGBELASE VINCENT NWACHOLUNDU S2015/183
131 OHWOFAOHWORAYE EJOVWOKE MATTHEW
S2015/185
132 IDOWU FUNMILOLA FISAYO S2015/186
133 OGHENE OLAWUNI RACHEAL (MRS) S2015/191
134 OLUWASEYI OLUKOLADE HENRY S2015/193
135 BAMIROLA AYINDE OBEY S2015/199
136 YUSUFF MUSILIU ADEKUNLE S2015/209
137 ODUNAIYA ADEBAYO KAZEEM S2015/211
138 LEOSO TEMITOPE AYOBAMI S2015/214
139 OLANIYI JOSEPH OLUGBENGA S2014/215
140 AKADIRI OPEYEMI AYODEJI S2015/218
141 ADENOTE ABIODUN AKINOLA S2015/219
142 EGENAMBA JULIET NGOZI (MRS) S2015/221
143 ADETAYO ADEWALE GABRIEL S2015/222
144 SULEIMAN ABDULKADIR MUHAMMED S2015/224
145 MAKADAS JACOB KOGI S2015/225
146 DABO ALIYU MAITALA S2015/232
147 ABOLARIN OLADEPO JAMIU S2015/234
148 OGALUZO CHUKWUKADIBIA JAMES S2015/235
149 IWUANYANWU PATRICK EMEKA S2015/238
150 ONODAGU JOSEPHAT CHIBUIKE S2015/239
151 NEGEDU ACHIMUGU AMOS S2015/240
152 UKEBHO FELIX OSEIWE S2015/247
153 OLADENI OLUBAYO TUNDE S2015/248
154 ABEJIDE OLUBUSUYI JOSEPH S2015/249
155 EZUGWU FRANCIS CHINEDU S2015/254
156 OTOBO FRANCIS NWADIOGOR S2015/255
157 SALIHU MOHAMMED SANNI S2015/260
158 TIJANI SAHEED ADELANI S2015/261
159 FEMI-SOYOMBO GLORIA LIFIN (MRS) S2015/265
160 NJOKU RICHARD EBERE S2015/269
161 JAMES GODSTIME KADIRI S2015/277
162 ADAM JULIUS JUMMAI S2015/278
163 ONITIRI SUNDAY ADEPOJU MICHAEL S2015/280
164 UMOREN VICTOR UDO S2015/285
165 JIBRIL MUHAMMED OLANREWAJU S2015/290
166 OMOTUNDE OLUFEMI SUNDAY S2015/292
167 ADEBOLA PAUL S2015/294
168 ABDULAZEEZ OZOVEHE ADAM S2016/001
169 ABDULLAHI UMAR S2016/003
170 ABUBAKAR TAKANA S2016/004
171 ADEBAYO AKANJI NURENI S2016/005
172 ADEBISI RASHEED ABIODUN S2016/006
173 ADEBIYI PRECIOUS KEHINDE (MRS) S2016/007
174 ADEOSUN ABASS ADEWALE S2016/011
175 ADETORO MUSA OLAJIDE S2016/014
176 ADEYEYE ADEDAYO ABIMBOLA S2016/020
177 AGU IZUCHUKWU CHARLES S2016/029
178 AGWU OGONNA ROBERT S2016/030
179 AHMADU HUSSEIN ADOMU S2016/031
180 AJAYI ABIODUN ADENIYI S2016/033
181 AKANDE ADEGOKE WALIU S2016/035
182 AKANDE GBENGA ABDULLAHI S2016/036
183 AKINADE KAYODE TIMOTHY S2016/037
184 AKINTOLA SAMUEL ADEWALE S2016/040
185 AKPAN UWEM IME S2016/042
186 AKPOROBARO OGHOGHO MARY S2016/044
187 ALATISE RAHMAN OPEYEMI S2016/045
188 ALONGE PETER ABIODUN S2016/047
189 AMADI MICHAEL CHIKA S2016/048
190 AMODU ADEBOWALE RASAKI S2016/050
191 AMODU ASSUMPTA NOAH S2016/051
192 APOLLOS MOSES S2016/055
193 AWAIYE OLAJIDE QUADRI S2016/058
194 AWODELE JOHN OLUGBENGA S2016/059
195 AYOOLA ABIODUN RIDMAN S2016/060
196 AYOOLA SAHEED BOLAJI S2016/061
197 BADMUS ABDURAHMON OLATUNJI S2016/063
198 BAKARE WAKEEL OLADELE S2016/064
199 BAKO MICHAEL S2016/065
200 BAMIDELE ADEBAYO OLAYINKA S2016/066
201 BAMIGBOYE LEKAN TIMOTHY S2016/067
202 BELLO LUCY S2016/070
203 BELLO OLUWASEUN OLABISI S2016/073
204 BEM ABEL ASOO S2016/074
205 BIOBAKU OLUWAFUNMINIYI OMOTAYO S2016/075
206 BOYEJO DAVID ADISA S2016/077
207 CHUKWU PATRICK UKAUKWU S2016/079
208 DABAI MOHAMMED ISA S2016/081
209 DADA OLUWAFEMI KADRI S2016/082
210 YAKO DANJUMA BMIBMITAUZA S2016/089
211 EDET EMEMOBONG USEN S2016/092
212 EDOKOR MATHEW AFEM S2016/093
213 EFFIONG SONIA AKPAN (MISS) S2016/096
214 EKPENYOUNG EFIOM EDEM S2016/100
215 EKUBO AYIBATARI TOBIN S2016/102
216 EKUNDAYO ESTHER LOVETH (MRS) S2016/103
217 EMBERGA MNUZUGHUL DICKSON S2016/105
218 EMIOLA BAKARE OLADIWURA ISAIAH S2016/107
219 ENAYABA EMEFIELE NELSON S2016/108
220 EREBI NELSON AVURA S2016/111
221 ESSIEN AKPAN JOHNSON S2016/114
222 ETUK AKANIYENE S2016/118
223 ETUK ANIETIE SUNDAY S2016/119
224 EZEOCHA-UCHECHI AUSTIN S2016/121
225 FABUNMI ROTIMI JOSEPH S2016/122
226 FAGUNLEKA KOLADE OLUSEYI S2016/123
227 FASINA OLAJIDE PAUL S2016/127
228 FATEYE BAMIDELE OLABODE S2016/128
229 FATOYINBO AYO OLALEKAN S2016/129
230 FETUGA ADEDAYO ADEYEMI S2016/130
231 FUNSHO-SALAWU AYODEJI OLUWAMUYIWA
S2016/131
232 GANA ISAAC S2016/132
233 GARBA MUHAMMED S2016/133
234 GEORGE SOALA BOBIRIBI S2016/134
235 GEORGE VICTOR TUPERE S2016/135
236 HAASTRUP ABIODUN ADEAYO S2016/136
237 HAMMAN EZEKIEL S2016/137
238 HARUNA ABDULLAHI S2016/138
239 HASSAN IBRAHIM S2016/140
240 IBRAHIM MUSA MAHMUD S2016/143
241 IBRAHIM PIUS ONOJA S2016/144
242 IDOWU AYODEJI ISAAC S2016/149
243 IDOWU JAMIU AKINDEINDE S2016/150
244 IDU EMMANUEL YAHAYA S2016/151
245 IJABOYEDE CHRISTIANAH FAYOKEMI(MRS)
S2016/155
246 IJEH CHUKWUNONSO DANIEL S2016/156
247 ILESANMI ADEWALE JAMES S2016/160
248 INYAMA LUCAS UDODIMMA S2016/162
249 ISADARE TOLULOPE MOTUNRAYO (MRS) S2016/164
250 ISHAYA ELKANA TAL S2016/166
251 KAREEM OLUSEUN S2016/174
252 KAREEM TEMITOPE RISQOT S2016/175
253 KOLAJO OLAYIWOLA SUNDAY S2016/177
254 KONKO AZUKA CHRISTOPHER S2016/179
255 LA’AH JOSHUA JONAH S2016/180
256 LASISI KAMIL OLURANTI S2016/181
257 LAWAL AUGUSTINE OLUWAFEMI S2016/182
258 LEIGH TOLULOPE OLUTAYO S2016/183
259 MAHMOUD KALTUME SULEIMAN S2016/185
260 MAIKANO SAMSON S2016/186
261 MARVE MNGUHENEN FUNMILAYO (MRS) S2016/187
262 MICHAEL DABERECHI EMMANUEL S2016/188
263 MKPARU MBAZULIKE S2016/189
264 MOCHA IFEANYICHUKWU OBI S2016/190
265 MOHAMMED ABDULLAHI MAIKANO S2016/191
266 MOSES MEFE S2016/192
267 NJOKU CHIBUIKE MICHAEL S2016/199
268 NKEREUWEM INIEKUNG EFIONG S2016/200
269 NWAKA OKWUCHUKWU CHRISTOPHER S2016/202
270 NWAOBI OBIAJULU FRANKLIN S2016/204
271 NWARU IFEANYICHUKWU S2016/205
272 NWONODI OVINUCHI S2016/207
273 NWOSU CHINWENDU STELLA S2016/208
274 NWOSU UZOCHI FAVOUR S2016/209
275 OBA-ALUKO HAMEEDAH BIMBO (MRS) S2016/211
276 OCHONU EZEKIEL UMORU S2016/217
277 ODESANMI ANTHONY OLATUNJI S2016/219
278 ODUNFA AJIBOLA (MRS.) S2016/222
279 OFFOR EMMANUEL CHIDIEBERE S2016/224
280 OGUNGBADE OLATUNJI S2016/231
281 OGUNGBENRO ADE SUNDAY S2016/232
282 OGUNTOYE SUNDAY OYENIYI S2016/234
283 OGUNYIPE KAYISAN OLOLADE (MRS) S2016/236
284 OJO EMWANTAIDE PETER S2016/237
285 OKAFOR ONYINYE PAMELA S2016/242
286 OKOROCHA VINCENT CHIKA S2016/246
287 OKUNEYE BABATUNDE OKUNYI S2016/247
288 OLADAPO OLUKUNLE STEPHEN S2016/248
289 OLADELE DEJI AUGUSTINE S2016/249
290 OLADIJO IRETI AUGUSTINE S2016/250
291 OLALERE OLADAYO AKINTUNDE S2016/251
292 OLATUNDE GBEMISOLA S2016/252
293 OLOFINTILA MUYIWA TOBI S2016/253
294 OLORUNTOLA OMOTOYOSI AYODEJI S2016/257
295 OLUFISAYO OLUYEMI S2016/260
296 OMEJE FERDINAND CHUKWUKA S2016/262
297 OMEJE UCHENNA VICTOR S2016/263
298 OMOTUNDE ADEMOLA ISHAQ S2016/265
299 WOMILOJU AHMED ABIODUN S2016/268
300 ONAH CHARLES EGWU SUNDAY S2016/269
301 ONAH KENNETH CHUKWUMA S2016/270
302 ONALAGUN IBRAHIM ADEMOLA S2016/272
303 ONI ADEGOKE S2016/273
304 ONILEGBALE IBRAHIM ABIODUN S2016/274
305 ONUIGBO IFEANYI CHUKWUDI S2016/275
306 ONWUMERE OJINNAKA VINCENT S2016/276
307 ONYEOZIRI CHINENYEZE HENRY S2016/277
308 WATHANAFA ABUBAKAR MARKA S2016/278
309 ONYIRI ESOR CHUKWUEMEKA S2016/279
310 OPE ZACCHEAUS OLUMUYIWA S2016/280
311 ORIMOLADE JACOB MAYOWA S2016/284
312 OSENI AYOKUNLE EBENEZER S2016/288
313 OSUM OKECHUKWU PAULINUS S2016/289
314 OSUNTOLA GBOLA OLUBUKOLA S2016/290
315 OTIKO AYOOLA OLUWATOBI S2016/291
316 OWOLABI SUNDAY MICHAEL S2016/294
317 OYELEYE OYELADUN OLAJUMOKE S2016/295
318 RAJI IBRAHIM MOHAMMED S2016/299
319 RASHEED RAHMAN BABATUNDE S2016/300
320 RUFAI YAKUBU S2016/301
321 SAADULLAHI IBRAHIM S2016/302
322 SADIQ OLUWATOMILAYO QUADRI S2016/303
323 SAKARIYAU MUIDEEN ADIO S2016/304
324 SALMAN YAKUBU S2016/307
325 SANNI AKANDE LUQMAN S2016/309
326 SANNI SURAJUDEEN AYOBAMI S2016/310
327 SANUSI AKINOLA ADEOLUWA S2016/311
328 SATURDAY CHUKUBEREDUKO NELSON S2016/312
329 SHITTU OLA ABDULGANIY S2016/313
330 SHITTU SAHEED OLAYEMI S2016/314
331 SOLADOYE ISAAC ADEOLA S2016/316
332 TUKUR MAHMUD S2016/319
333 UDENANI YAGAZIE ARIHUR S2016/322
334 UDOH EMEM DEBORAH (MRS) S2016/324
335 UDOMESSIEN ETIETTE ETIM S2016/325
336 UGWOKE CHIDOZIE BENJAMIN S2016/326
337 UKAEGBU SUNDAY ALEXANDER S2016/329
338 UKPOSI OSISIOMA PAUL S2016/331
339 UMOH NDITI-EDIM UDO S2016/332
340 USMAN ADAMU S2016/334
341 UWAJE ANDREW UZOR S2016/335
342 YA'U ABUBAKAR ZAKARI S2016/339
343 AKALA OLADIPUPO S2011/066
B. ENROLMENT OF PUPIL SURVEYORS
The following candidates passed the Direct Examination
into the Pupil Surveyor’s cadre.
1 EBULU JOSEPH ODION P2012/003
2 AKPAH EMMANUEL ENEBI P2012/012
3 JUNAID TUNDE OLADIPUPO P2014/003
4 IDAKWOJI BENJAMIN IMADI P2014/004
5 JOEL MOSES ADAMS P2014/010
6 SAADU WAHEED ZARUMI P2014/012
7 ADEYEYE JULIET ADEOLA (MRS) P2014/020
8 ARINDE RACHAEL ADEBOLA P2015/001
9 AHMED MOHAMMED GBALE P2015/002
10 PETER OLOBO P2015/005
11 OGUNLADE IDOWU MATTHEW P2015/006
12 OLAGUNJU ABIMBOLA SOLOMON P2015/009
13 AMPITAN TEMITOPE STEPHEN P2015/015
14 ERONDU CYRIL CHIJIUBA P2015/016
15 NSON MICAH ANSHAK P2015/018
16 EMENIKE AUSTIN ONYEKACHI P2015/021
17 UZOGOR ZELUWA LEO P2015/022
18 CHIGBU ALOZIE P2015/029
19 ORHIUNU LONDON P2015/033
20 AREMU TAIWO OLUWASOLA P2015/034
21 DOSUNMU OLUWASHOGO ISAAC P2015/037
22 OSAINAIKE VICTOR ADURAGBEMI P2015/039
23 ADEJUMOBI EBENEZER GBENRO P2016/001
24 ADEWOLE STEPHEN ADEBAYO P2016/002
25 ALLI-BALOGUN OLUSEGUN MUKAILU P2016/005
26 BATURE JONATHAN GODWIN P2016/007
27 BELLO ALIU AYODELE P2016/008
28 BELLO FELIX DIRAN P2016/009
29 LAWSON NWIDUM P2016/013
30 MAKAMA ISHAYA ZHEOKEH P2016/014
31 OYATAYO FUNMILAYO JUMOKE P2016/022
32 OYENPEMI CLEMENT OYEDARE P2016/024
33 TARIAH VICTOR PATRICK SONY P2016/025
34 GARUBA LOVE ABDULAZEEZ P2016/032
35 OLADELE FUNMILOLA (MRS) P2016/033
36 OJO AKINTUNDE TITILOPE P2016/035
37 TAIWO COMFORT ADEBOLA (MRS) P2016/046
38 IYALEKHUE COLLINS OSARUYI P2016/056
SURV. SULEIMAN HASSAN
REGISTRAR

Fomular used to calculate areà of triangle and any type of irregular plots

Try it works

Saturday, 10 December 2016

Total Station Operations

Lesson Note On How to used total station

Total Station Topographic Survey

Description Using a total station and one or more pole-mounted reflecting prisms, plot all topographic features and any additional ground shots that are required to accurately define the terrain. See Figure D.l0. 

Equipment:Total station and one, or more, pole-mounted reflecting prisms. 

Procedure:

• Set the total station over a known control point (northing, easting, and elevation known). 

• Set the program menu to the type of survey (topography) being performed and to the required instrument settings. Select the type of field data to be stored (e.g., N, E, and Z, or E, N, and Z, etc.). Set the temperature and pressure settings-if required. 

• Check configuration settings, for example, tilt correction, coordinate format, zenith vertical angle, angle resolution (e.g., 5"), c + r correction (e.g., no.), units (ft/m, degree, mm Hg), and auto power off (say, 20'). 

• Identify the instrument station from the menu. Insert the date, station number coordinates, elevation, and Hi. 

• Backsight to one or more known control point(s) (point number, north and east coordinates, and elevation known). Set the horizontal circle to 0°00'00" or to some assigned reference azimuth for the backsight reference direction. Store or record the data. Measure and store the reflector height. 

• Set the initial topography point number in the instrument (e.g., 1,000), and set for automatic point number incrementation. 

• Begin taking I.Ss. Most total stations have an automatic mode for topographic surveys, where one button-push will measure and store all the point data. 

• Put all or some selected point numbers on the field sketch. These field notes will be of assistance later in the editing process if mistakes have occurred. 

• When all required points have been surveyed, check into the control station originally back sighted to ensure that the instrument orientation is still valid. 

• Transfer the field data into a properly labeled file in a computer. 

• After opening the data processing program, import the field data file and begin the editing process and the graphics generation process. 

• Create the TIN (Triangulated Integrated Network) and Contours. 

• Either finish the drawing with the working program or finish it on a CAD program. 

• Prepare a plot file and then plot the sheet on scale. 

Reference: Surveying with Construction Applications Seventh Edition 

Leveling operations

Levelling ( or Leveling ) is a branch of surveying, the
object of which is: i) to find the elevations of given
points with respect to a given or assumed datum,
and ii) to establish points at a given or assumed
datum. The first operation is required to enable the
works to be designed while the second operation is
required in the setting out of all kinds of engineering
works. Levelling deals with measurements in a
vertical plane.
Level surface: A level surface is defined as a curved
surface which at each point is perpendicular to the
direction of gravity at the point. The surface of a still
water is a truly level surface. Any surface parallel to
the mean spheroidal surface of the earth is,
therefore, a level surface.
Level line: A level line is a line lying in a level surface.
It is, therefore, normal to the plumb line at all points.
Horizontal plane: Horizontal plane through a point is
a plane tangential to the level surface at that point. It
is, therefore, perpendicular to the plumb line through
the point.
Horizontal line: It is a straight line tangential to the
level line at a point. It is also perpendicular to the
plumb line.
Vertical line: It is a line normal to the level line at a
point. It is commonly considered to be the line
defined by a plumb line.
Datum: Datum is any surface to which elevation are
referred. The mean sea level affords a convenient
datum world over, and elevations are commonly
given as so much above or below sea level. It is often
more convenient, however, to assume some other
datum, specially, if only the relative elevation of
points are required.
Elevation: The elevation of a point on or near the
surface of the earth is its vertical distance above or
below an arbitrarily assumed level surface or datum.
The difference in elevation between two points is the
vertical distance between the two level surface in
which the two points lie.
Vertical angle: Vertical angle is an angle between two
intersecting lines in a vertical plane. Generally, one of
these lines is horizontal.
Mean sea level: It is the average height of the sea for
all stages of the tides. At any particular place it is
derived by averaging the hourly tide heights over a
long period of 19 years.
Bench Mark: It is a relatively permanent point of
reference whose elevation with respect to some
assumed datum is known. It is used either as a
starting point for levelling or as a point upon which to
close as a check.
Methods of levelling
Three principle methods are used for determining
differences in elevation, namely, barometric levelling,
trigonometric levelling and spirit levelling.
Barometric levelling
Barometric levelling makes use of the phenomenon
that difference in elevation between two points is
proportional to the difference in atmospheric
pressures at these points. A barometer, therefore,
may be used and the readings observed at different
points would yield a measure of the relative elevation
of those points.
At a given point, the atmospheric pressure doesn’t
remain constant in the course of the day, even in the
course of an hour. The method is, therefore, relatively
inaccurate and is little used in surveying work except
on reconnaissance or exploratory survey.
Trigonometric Levelling (Indirect Levelling)
Trigonometric or Indirect levelling is the process of
levelling in which the elevations of points are
computed from the vertical angles and horizontal
distances measured in the field, just as the length of
any side in any triangle can be computed from proper
trigonometric relations. In a modified form called
stadia levelling, commonly used in mapping, both the
difference in elevation and the horizontal distance
between the points are directly computed from the
measured vertical angles and staff readings.
Spirit Levelling (Direct Levelling)
It is that branch of levelling in which the vertical
distances with respect to a horizontal line
(perpendicular to the direction of gravity) may be
used to determine the relative difference in elevation
between two adjacent points. A horizontal plane of
sight tangent to level surface at any point is readily
established by means of a spirit level or a level vial. In
spirit levelling, a spirit level and a sighting device
(telescope) are combined and vertical distances are
measured by observing on graduated rods placed on
the points. The method is also known as direct
levelling. It is the most precise method of
determining elevations and the one most commonly
used by engineers.
Levelling Instruments
The instruments commonly used in direct levelling
are:
1. A level
2. A levelling staff

History of GIS

Geoinformatics is the science and the technology
which develops and uses information science
infrastructure to address the problems of geography ,
cartography , geosciences locations and related
branches of science and engineering.
Overview
Geoinformatics has been described as "the science and
technology dealing with the structure and character of
spatial information, its capture, its classification and
qualification, its storage, processing, portrayal and
dissemination, including the infrastructure necessary
to secure optimal use of this information" [1] or "the
art, science or technology dealing with the acquisition,
storage, processing production, presentation and
dissemination of geoinformation". [2]
Geomatics is a similarly used term which encompasses
geoinformatics, but geomatics focuses more so on
surveying . Geoinformatics has at its core the
technologies supporting the processes of acquiring,
analyzing and visualizing spatial data. Both geomatics
and geoinformatics include and rely heavily upon the
theory and practical implications of geodesy.
Geography and earth science increasingly rely on
digital spatial data acquired from remotely sensed
images analyzed by geographical information systems
(GIS) and visualized on paper or the computer screen.
[3]
Geoinformatics combines geospatial analysis and
modeling, development of geospatial databases,
information systems design, human-computer
interaction and both wired and wireless networking
technologies. Geoinformatics uses geocomputation
and geovisualization for analyzing geoinformation .
Branches of geoinformatics include:
Cartography
Geodesy
Global Navigation Satellite Systems
Photogrammetry
Remote Sensing
Spatial Analysis
Web mapping
Research
Research in this field is used to support global and
local environmental, energy and security programs.
The Geographic Information Science and Technology
group of Oak Ridge National Laboratory is supported
by various government departments and agencies
including the United States Department of Energy . It is
currently the only group in the United States
Department of Energy National Laboratory System to
focus on advanced theory and application research in
this field. There are also a lot of interdiscipline
research involved in geoinformatics fields including
computer science, information technology, software
engineering, biogeography, geography, conservation,
architecture, spatial analysis and reinformacement
learning.
Applications
Many fields benefit from geoinformatics, including
urban planning and land use management, in-car
navigation systems, virtual globes, public health, local
and national gazetteer management, environmental
modeling and analysis, military, transport network
planning and management, agriculture, meteorology
and climate change, oceanography and coupled ocean
and atmosphere modelling, business location planning,
architecture and archeological reconstruction,
telecommunications, criminology and crime simulation,
aviation, biodiversity conservation and maritime
transport. The importance of the spatial dimension in
assessing, monitoring and modelling various issues
and problems related to sustainable management of
natural resources is recognized all over the world.
Geoinformatics becomes very important technology to
decision-makers across a wide range of disciplines,
industries, commercial sector, environmental agencies,
local and national government, research, and
academia, national survey and mapping organisations,
International organisations, United Nations, emergency
services, public health and epidemiology, crime
mapping, transportation and infrastructure, information
technology industries, GIS consulting firms,
environmental management agencies), tourist industry,
utility companies, market analysis and e-commerce,
mineral exploration, etc. Many government and non
government agencies started to use spatial data for
managing their day-to-day activities.

Survey as a profession

Surveying or land surveying is the technique,
profession, and science of determining the terrestrial
or three-dimensional position of points and the
distances and angles between them. A land surveying
professional is called a land surveyor . These points are
usually on the surface of the Earth, and they are often
used to establish land maps and boundaries for
ownership , locations like building corners or the
surface location of subsurface features, or other
purposes required by government or civil law, such as
property sales.
Surveyors work with elements of geometry,
trigonometry , regression analysis, physics ,
engineering, metrology, programming languages and
the law. They use equipment like total stations , robotic
total stations, GPS receivers, retroreflectors , 3D
scanners , radios, handheld tablets, digital levels,
drones, GIS and surveying software.
Surveying has been an element in the development of
the human environment since the beginning of
recorded history. The planning and execution of most
forms of construction require it. It is also used in
transport , communications, mapping, and the
definition of legal boundaries for land ownership. It is
an important tool for research in many other scientific
disciplines.
Definitions
ACSM
The American Congress on Surveying and Mapping
(ACSM), defines surveying as the science and art of
making all essential measurements to determine the relative
position of points or physical and cultural details above,
on, or beneath the surface of the Earth, and to depict them
in a usable form, or to establish the position of points or
details. [citation needed ]
Also per ACSM, the type of surveying known as "land
surveying" is the detailed study or inspection, as by
gathering information through observations, measurements
in the field, questionnaires, or research of legal
instruments, and data analysis in the support of planning,
designing, and establishing of property boundaries. It
involves the re-establishment of cadastral surveys and land
boundaries based on documents of record and historical
evidence, as well as certifying surveys (as required by
statute or local ordinance) of subdivision plats or maps,
registered land surveys, judicial surveys, and space
delineation. Land surveying can include associated services
such as mapping and related data accumulation,
construction layout surveys, precision measurements of
length, angle, elevation, area, and volume, as well as
horizontal and vertical control surveys, and the analysis
and utilization of land survey data.

**who is a Surveyor

A surveyor is a professional person with
the academic qualifications and technical
expertise to conduct one, or more, of the
following activities;
to determine, measure and represent
land, three-dimensional objects, point-
fields and trajectories;
to assemble and interpret land and
geographically related information,
to use that information for the planning
and efficient administration of the land,
the sea and any structures thereon; and,
to conduct research into the above
practices and to develop them.

Different Between Old and new survey equipment

A surveyor depends on their equipment for
acquiring accurate measurements quickly and
easily. The article describes the various types of
surveying equipment, both ancient and modern,
that are available in the market today.
Many kinds of surveying equipment have been
used in the past and present to help a surveyor
measure various parameters of a land area. Each
of these parameters is measured by a specific
type of measuring equipment. In this article we
will learn about the importance of the main types
of surveying equipments, both old and new.
Surveying Equipments - Old
In ancient times surveying equipment included
chains, compass, solar compass, transit,
theodolite and more. Chains with equal size links
were used to measure distance between two
required points. A compass was used to measure
the direction of a line that was being surveyed. A
solar compass was used for measuring both the
direction and latitude of a particular point with the
help of sun and stars. A Solar Compass could also
measure horizontal angles and the “true north" of
a particular place. A metallic measuring tape was
used to measure shorter distances.
As technology gradually advanced with time,
instruments used for surveying also improved.
Horizontal and vertical angles were measured
using a simple theodolite whereas different heights
were measured by a basic level. Measuring wheels
were also initially used by surveyors to measure
long distances in a short duration of time.
Measuring wheels came in two types: mechanical
and electrical, and both worked on the same
principle of rolling the wheel from the start to the
end point.
In the early 1900s, surveyors started to use
surveying equipment such as planimeters,
theodolites, automatic levels and measuring
wheels. A planimeter is the best known tool for
measuring asymmetrical land areas as they
eliminate the need for charts or manual
calculations; whereas a theodolite allows
measuring of horizontal and vertical angles. A
theodolite consists of a movable telescope
attached over perpendicular axis. It provides
precise measurement of angles and is an integral
part of every surveying tool kit. A transit is a type
of theodolite but has less precision.
An auto level or a dumpy level is also a type of
surveying equipment used for measuring
horizontal levels. It consists of a telescope like
device fitted on a tripod stand. Auto level, tilting
level, and self-leveling level are all types of leveling
instruments, each providing different rotating
capabilities.
Most surveying instruments are fixed on a tripod,
which acts as a support. As the name suggests,
tripods have three legs with length varying
capability. Many of these equipments are still used
by surveyors around the world.
Surveying Equipments - New
Recent development in technology has provided
some of the finest surveying equipments present
today. Moreover, with the introduction of global
positioning system, the methods of surveying
have also totally changed. GPS has not only made
surveying faster but has increased the accuracy to
amazing heights. GPS works with the help of
satellite systems which provide accurate data
directly on the computer screen. Various types of
GPS equipment is available, from basic to highly
advanced. Some GPS equipment even have night
vision which facilitates surveying during the night
time. However, it is said that though GPS helps in
acquiring the exact position of the land; it does
not provide good results in dense forest areas or
concrete constructions. For this reason, an
instrument known as total station is used along
with the GPS.
Total station is a
theodolite with an
Electronic Distance
Measurement Device.
Total station has also
been one of the reasons
behind the drastic
change of technology in
the surveying field.
EDMD shifted the
surveying technology
from optical mechanical devices to digital
electronic devices. In spite of just being distance
measuring equipment, total station can also be
used for leveling when adjusted in a horizontal
plane. Most of the ultra-modern surveying devices
are a combination of one or more of these
devices.
There is a long list of surveying equipment
available in the market today. The selection of
particular equipment depends on the type of
application and accuracy required. Though all
these equipment provide a wide range of options
to surveyors, it is advisable to have a thorough
knowledge of both, the equipment and the desired
survey. This would not only help in bringing
accuracy to the work but would also save
considerable time and money.

Application of Topographical Surveyinv

Topographic Surveys are used to identify and map the
contours of the ground and existing features on the
surface of the earth or slightly above or below the
earth's surface (i.e. trees, buildings, streets, walkways,
manholes, utility poles, retaining walls, etc.). If the
purpose of the survey is to serve as a base map for the
design of a residence or building of some type, or design
a road or driveway, it may be necessary to show
perimeter boundary lines and the lines of easements on
or crossing the property being surveyed, in order for a
designer to accurately show zoning and other agency
required setbacks.
Topographic Surveys require "bench marks" to which
ground contours are related, information regarding
surface and underground utilities, determination of
required setbacks, etc.

Friday, 9 December 2016

Calculation of area of irregular surface using Simpsons method

Methods of Calculation
of Areas in Surveying |

Simpson’s Rule

Calculation of Areas in Surveying | Simpson’s Rule
In one of my previous articles, I discussed Midpoint
Ordinate Rule and Average Ordinate Rule in detail with an
example and listed out various important methods used
for the calculation of areas in Surveying. In this article,
we will deal with the next important method (rule) i.e.
Simpson’s Rule along with a numerical example used for
the calculation of areas in the field of Surveying.
Here are the five important rules (Methods) used for the
calculation of areas in Surveying:

1. Midpoint ordinate rule
2. Average ordinate rule
3. Simpson’s rule
4. Trapezoidal rule
5. Graphical rule

Simpson’s Rule
Statement

It states that, sum of first and last ordinates has to be
done. Add twice the sum of remaining odd ordinates and
four times the sum of remaining even ordinates. Multiply to
this total sum by 1/3rd of the common distance between the
ordinates which gives the required area.
Where O 1, O 2, O 3 , …. O n are the lengths of the
ordinates
d = common distance
n = number of divisions
Note:

This rule is applicable only if ordinates are odd, i.e. even
number of divisions.
If the number of ordinates are even, the area of last
division maybe calculated separated and added to the
result obtained by applying Simpson’s rule to two
remaining ordinates.
Even if first or last ordinate happens to be zero, they are
not to be omitted from Simpson’s rule.
The following offsets are taken from a chain line to an
irregular boundary towards right side of the chain line.

Chainage 0       25      50.         75     100    125   150

Offset ‘m’ 3.6   5.0      6.5        5.5   7.3.     6.0      4.0

Common distance, d = 25m

Area = d/3[(O 1+O 7) + 2 (O 3 +O 5)+4(O 2+O4+O 6)]
= 25/3[(3.6+4)+2(6.5+7.3)+4(5+5.5+6)]
Area = 843.33sqm

How to set up a Theodolite

Temporary adjustments are set of operations which
are required to be done on an instrument ( theodolite)
in order to make it ready for taking observations.
Temporary adjustments of theodolite include its
setting up, centering, leveling up and elimination of
parallax. Therefore these adjustments can be achieved
in 4 steps:-
Setting
Centering
Levelling
Focusing
Setting
The setting operation includes fixing the theodolite
with tripod along with approximate levelling and
centering over the station mark. For setting up the
instrument, the tripod is placed over the station with
its legs widely spread so that the centre of the tripod
head lies above the station point and its head
approximately level (by eye estimation). The
instrument is then fixed with the tripod by screwing
through trivet. The height of the instrument should be
such that observer can see through telescope
conveniently. After this, a plumb bob is suspended
from the bottom of the instrument and it should be
such that plumb bob should point near to the station
mark.
Centering
Centering implies that bringing vertical axis of
theodolite immediately over station mark.[1] To do this
the following procedure is followed:-
First, the approximate centring of the instrument is
done by moving the tripod legs radially or
circumferentially as per need of the circumstances.
It may be noted that due to radial movement of the
legs, plumb bob gets shifted in the direction of the
movement of the leg without seriously affecting the
level of the instrument. On the other hand, when the
legs are moved side ways or circumferentially, the
plumb does not shift much but the level gets affected.
Sometimes, the instrument and the tripod have to be
moved bodily for centring. It must be noted that the
centering and leveling of instrument is done
recursively. Finally, exact centring is done by using the
shifting head of the instrument. During this, first the
screw-clamping ring of the shifting head is loosened
and the upper plate of the shifting head is slid over
the lower one until the plumb bob is exactly over the
station mark. After the exact centring, the screw
clamping ring gets tightened.
Levelling
Leveling of an instrument is done to make the vertical
axis of the instrument truly vertical. For accurate
levelling the following steps are strictly followed:-
1. Bring one of the level tube parallel to any two of
the foot screws, by rotating the upper part of the
instrument.
2. The bubble is brought to the centre of the level
tube by rotating both the foot screws either inward or
outward. The bubble moves in the same direction as
the left thumb.
3. The bubble of the other level tube is then brought
to the centre of the level tube by rotating the third foot
screw either inward or outward. [In step 1 itself, the
other plate level will be parallel to the line joining the
third foot screw and the centre of the line joining the
previous two foot screws.]
4. Repeat Step 2 and step 3 in the same quadrant till
both the bubble remain central.
5. By rotating the upper part of the instrument
through 180°, the level tube is brought parallel to first
two foot screws in reverse order. The bubble will
remain in the centre if the instrument is in permanent
adjustment.
Otherwise, repeat the whole process starting from
step1 to step5.
Focusing
To obtain the clear reading, the image formed by the
objective lens should fall in the plane of diaphragm
and the focus of eye-piece should also be at the plane
of diaphragm . This is being carried out by removing
parallax by proper focusing of objective and eye-piece.
Thus, focusing operation involves two steps:
Focusing of eye-piece .
For focusing of the eye piece, point the telescope to
the sky or hold a piece of white paper in front of
telescope. Move the eye-piece in and out until a
distinct sharp black image of the cross-hairs is seen.
This confirms proper focusing. [2]
Focusing of object glass.
It is done for each independent observation to bring
the image of the object in the plane of cross hairs. It
includes following steps of operation: First, direct the
telescope towards the object for observation. Next,
turn the focusing screw until the image of the object
appears clear and sharp as the observer looks through
properly focused eye-piece. If focusing has been done
properly, there will be no parallax i.e., there will be no
apparent movement of the image relative to the cross
hairs if the observer moves his eye from one side to
the other or from top to bottom.